New Year, New Progress: January 2026 Project Highlights
January 27, 2026
|By Kelly Hawks
Headquarters
- The design team is preparing the Schematic Design Drawing Set for the Headquarters project. The next step will be to review and incorporate stakeholder feedback.
- Project bidding is expected to begin in the first quarter of 2026. Following bidding, contractor selection and contract finalization will take place.
Station 31
- A preconstruction meeting with the city of Auburn is scheduled for the end of January 2026. Outcomes from this meeting will guide next steps in permitting and approvals.
- The design team is preparing the Schematic Design Drawing Set for Station 31.
- Construction is anticipated to start in Fall 2026, pending completion of permitting and contractor selection.
Station 36
- Construction is underway and progressing well.
- The Water Resistant Barrier (WRB) exterior panels are now complete.
- The steel canopy at the fuel fill station has been finished.
- Crews are focusing on mechanical, electrical, and plumbing rough-ins inside the building. Miscellaneous site work and roofing are ongoing as weather permits.
Station 38
- Land Use & SEPA permits are currently under review by the city.
- The building permit will be submitted within the next few weeks.
- Project bidding is set for the first quarter of 2026.
- The Station Design Committee has finalized material preferences, and architects are now updating renderings for review.
Stay tuned for more updates as these projects progress!