Skip to main content

Capital Facilities Update- August 2026

Administrative Headquarters 

Work began at the end of July 206, with completion in anticipated in Summer 2027. The project involves a complete interior remodel designed to better support the department’s needs and accommodate the various work groups. Bringing everyone together into a shared, functional space will improve communication, collaboration, and overall efficiency while creating a more cohesive and effective work environment.

Station 31 

The Station 31 team is currently in the permitting stage. We anticipate going to bid in Q1 of 2027, with construction expected to begin in Q2 2027.

Station 36

The Station 36 contractor is currently working through closeout documentation and completing the punch. The VRFA is anticipated to occupy the facility by the end of September

Station 38 

Station 38 construction broke ground in August 2026 and is anticipated to be completed in Fall 2027.

Privacy Preference Center